The work breakdown structure involves identifying the ________ for each activity.

admin
July 5, 2020 0 Comment

71) The work breakdown structure involves
identifying the ________ for each activity.
A) time
B) cost
C) resource requirements
D) predecessors
E) All of the above

72) PERT stands for
A) probabilistic evaluation and review
technique.
B) program evaluation and review
technique.
C) probability of expected run times.
D) program of expected run times.
E) project evaluation and review
technique.
73) CPM stands for
A) critical path management.
B) critical project management.
C) critical project method.
D) critical path method.
E) centralized project management.
74) Which of the following questions can
be answered by PERT?
A) When will the entire project be
completed?
B) What is the probability that the
project will be completed by a specific date?
C) What are the critical activities?
D) What are the noncritical activities?
E) All of the above
75) In PERT, we assume that
A) the times to complete individual
activities are known with certainty.
B) all activities are carried out by staff
from our own organization.
C) the total cost of a project is
independent of the time to complete the project.
D) the total time to complete all
activities on the critical path is described by a normal distribution.
E) None of the above
76) The two common techniques for drawing
PERT networks are
A) NOA and NRA.
B) AON and AOA.
C) GANTT and NOA.
D) ONA and OAO.
E) CAN and CAA.
77) In PERT analysis, the probability of
the optimistic time occurring should be on the order of
A) 1/2.
B) 1/3.
C) 1/6.
D) 1/10.
E) 1/100.
78) The expected time in PERT is
A) greater than the most likely time.
B) equal to the most likely time.
C) less than the most likely time.
D) Any of the above
E) None of the above
79) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 3, 7, and 11 days respectively,
compute the expected time for this activity.
A) 5
B) 6
C) 7
D) 12
E) None of the above

80) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute
the expected time for this activity.
A) 3
B) 4
C) 5
D) 6
E) None of the above

81) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 1, 9, and 23 days respectively,
compute the PERT expected activity time for this activity.
A) 10
B) 12
C) 9
D) 11
E) None of the above
82) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 3, 6, and 9 days respectively,
compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
E) None of the above
83) The project described by:

Activity

Immediate

Predecessor

Time
(days)

A

10

B

A

4

C

A

6

D

B

7

E

C

5

is best represented by which of the
following networks?
A)
.jpg”>
B)
.jpg”>
C)
.jpg”>
D)
.jpg”>
E) None of the above
84) The project described by:

Activity

Immediate

Predecessor

Time
(days)

A

10

B

A

4

C

A

6

D

B,
C

7

E

C

5

has a critical path of length of
A) 21 days.
B) 14 days.
C) 23 days.
D) 32 days.
E) None of the above

85) The project described by:

Activity

Immediate

Predecessor

Time
(days)

A

6

B

A

2

C

8

D

B,
C

5

E

D

7

has a critical path of length of
A) 15 days.
B) 20 days.
C) 17 days.
D) 18 days.
E) None of the above
86) Using the data in Table 11-4, what is
the minimum possible time required for completing the project?
A) 8
B) 12
C) 18
D) 10
E) None of the above
87) Using the data in Table 11-4, what is
the latest possible time that C may be started without delaying completion of
the project?
A) 0
B) 4
C) 8
D) 10
E) None of the above
88) Using the data in Table 11-4, compute
the slack time for activity D.
A) 0
B) 5
C) 3
D) 6
E) None of the above

89) Using the
data in Table 11-4, compute the latest finish time for activity E.
A) 4
B) 10
C) 14
D) 25
E) None of the above

90) Using the data in Table 11-4, determine
the latest time activity A can be started without delaying the project
completion.
A) 4
B) 3
C) 8
D) 6
E) None of the above
71) The work breakdown structure involves
identifying the ________ for each activity.A) timeB) costC) resource requirementsD) predecessorsE) All of the above72) PERT stands forA) probabilistic evaluation and review
technique.B) program evaluation and review
technique.C) probability of expected run times.D) program of expected run times.E) project evaluation and review
technique.73) CPM stands forA) critical path management.B) critical project management.C) critical project method.D) critical path method.E) centralized project management.74) Which of the following questions can
be answered by PERT?A) When will the entire project be
completed?B) What is the probability that the
project will be completed by a specific date?C) What are the critical activities?D) What are the noncritical activities?E) All of the above75) In PERT, we assume thatA) the times to complete individual
activities are known with certainty.B) all activities are carried out by staff
from our own organization.C) the total cost of a project is
independent of the time to complete the project.D) the total time to complete all
activities on the critical path is described by a normal distribution.E) None of the above76) The two common techniques for drawing
PERT networks areA) NOA and NRA.B) AON and AOA.C) GANTT and NOA.D) ONA and OAO.E) CAN and CAA.77) In PERT analysis, the probability of
the optimistic time occurring should be on the order ofA) 1/2.B) 1/3.C) 1/6.D) 1/10.E) 1/100.78) The expected time in PERT isA) greater than the most likely time.B) equal to the most likely time.C) less than the most likely time.D) Any of the aboveE) None of the above79) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 3, 7, and 11 days respectively,
compute the expected time for this activity.A) 5B) 6C) 7D) 12E) None of the above80) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute
the expected time for this activity.A) 3B) 4C) 5D) 6E) None of the above81) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 1, 9, and 23 days respectively,
compute the PERT expected activity time for this activity.A) 10B) 12C) 9D) 11E) None of the above82) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 3, 6, and 9 days respectively,
compute the PERT variance for this activity.A) 3B) 1C) 9D) 6E) None of the above83) The project described by:ActivityImmediate
PredecessorTime(days)A–10BA4CA6DB7EC5is best represented by which of the
following networks?A).jpg”>B).jpg”>C).jpg”>D).jpg”>E) None of the above84) The project described by:ActivityImmediate
PredecessorTime(days)A–10BA4CA6DB,
C7EC5has a critical path of length ofA) 21 days.B) 14 days.C) 23 days.D) 32 days.E) None of the above85) The project described by:ActivityImmediate
PredecessorTime(days)A–6BA2C–8DB,
C5ED7has a critical path of length ofA) 15 days.B) 20 days.C) 17 days.D) 18 days.E) None of the above86) Using the data in Table 11-4, what is
the minimum possible time required for completing the project?A) 8B) 12C) 18D) 10E) None of the above87) Using the data in Table 11-4, what is
the latest possible time that C may be started without delaying completion of
the project?A) 0B) 4C) 8D) 10E) None of the above88) Using the data in Table 11-4, compute
the slack time for activity D.A) 0B) 5C) 3D) 6E) None of the above89) Using the
data in Table 11-4, compute the latest finish time for activity E.A) 4B) 10C) 14D) 25E) None of the above90) Using the data in Table 11-4, determine
the latest time activity A can be started without delaying the project
completion.A) 4B) 3C) 8D) 6E) None of the above