In PERT, the variance in completion time is equal to the variance of the most time consuming activity on the critical path.

admin
July 5, 2020 0 Comment

31) In PERT, the variance in completion
time is equal to the variance of the most time consuming activity on the
critical path.

32) Given the assumptions in PERT, the
probability that a project will be completed in less time than required by the
activities on the critical path is approximately 50%.

33) Gantt charts and PERT diagrams provide
the same information, just in different formats.

34) Gantt charts contain information about
the time taken by each activity, but not about the sequential dependencies of
the activities.

35) Budgets are computed using only ES
times.

36) The value of work completed is
computed by multiplying budgeted cost by the percent completion.

37) Shortening a project is called
crashing.

38) The activity crash cost is equal to
the incremental cost of shortening the project.

39) The critical path of a network is the
A) shortest time path through the network.
B) path with the fewest activities.
C) path with the most activities.
D) longest time path through the network.
E) None of the above

40) In a PERT network, the earliest
(activity) start time is the
A) earliest time that an activity can be
finished without delaying the entire project.
B) latest time that an activity can be
started without delaying the entire project.
C) earliest time that an activity can
start without violation of precedence requirements.
D) latest time that an activity can be
finished without delaying the entire project.
E) None of the above

41) Slack time in a network is the
A) amount of time that an activity would
take assuming very unfavorable conditions.
B) shortest amount of time that could be
required to complete the activity.
C) amount of time that you would expect it
would take to complete the activity.
D) difference between the expected
completion time of the project using pessimistic times and the expected completion
time of the project using optimistic times.
E) amount of time that an activity can be
delayed without delaying the entire project.

42) The first step in planning and
scheduling a project is to develop the
A) employee scheduling plan.
B) PERT/CPM network diagram.
C) critical path.
D) work breakdown structure.
E) variance calculations for each
activity.
43) Which of the following is not a
concept associated with CPM?
A) normal time
B) probability
C) normal cost
D) crash cost
E) deterministic network
44) PERT
A) assumes that we do not know ahead of
time what activities must be completed.
B) assumes that activity time estimates
follow the normal probability distribution.
C) is a network technique that uses three
time estimates for each activity in a project.
D) is a deterministic network technique
that allows for project crashing.
E) None of the above

45) CPM
A) assumes we do not know ahead of time
what activities must be completed.
B) assumes that activity time estimates
follow the normal probability distribution.
C) is a deterministic network technique
that allows for project crashing.
D) is a network technique that allows
three time estimates for each activity in a project.
E) None of the above

46) Managers use the network analysis of
PERT and CPM to help them
A) derive flexibility by identifying
noncritical activities.
B) replan, reschedule, and reallocate
resources such as manpower and finances.
C) plan, schedule, monitor, and control
large and complex projects.
D) All of the above
E) None of the above

47) The expected time in PERT is
A) a weighted average of the most
optimistic time, most pessimistic time, and four times the most likely time.
B) the modal time of a beta distribution.
C) a simple average of the most
optimistic, most likely, and most pessimistic times.
D) the square root of the sum of the
variances of the activities on the critical path.
E) None of the above
48) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute
the PERT expected activity time for this activity.
A) 8
B) 6
C) 7
D) 9
E) None of the above

49) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 2, 5, and 14 days respectively,
compute the PERT expected activity time for this activity.
A) 6
B) 7
C) 9
D) 5
E) None of the above

50) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 4, 14, and 18 days respectively,
compute the PERT expected activity time for this activity.
A) 14
B) 12
C) 11
D) 13
E) None of the above
31) In PERT, the variance in completion
time is equal to the variance of the most time consuming activity on the
critical path.32) Given the assumptions in PERT, the
probability that a project will be completed in less time than required by the
activities on the critical path is approximately 50%.33) Gantt charts and PERT diagrams provide
the same information, just in different formats.34) Gantt charts contain information about
the time taken by each activity, but not about the sequential dependencies of
the activities.35) Budgets are computed using only ES
times.36) The value of work completed is
computed by multiplying budgeted cost by the percent completion.37) Shortening a project is called
crashing.38) The activity crash cost is equal to
the incremental cost of shortening the project.39) The critical path of a network is theA) shortest time path through the network.B) path with the fewest activities.C) path with the most activities.D) longest time path through the network.E) None of the above40) In a PERT network, the earliest
(activity) start time is theA) earliest time that an activity can be
finished without delaying the entire project.B) latest time that an activity can be
started without delaying the entire project.C) earliest time that an activity can
start without violation of precedence requirements.D) latest time that an activity can be
finished without delaying the entire project.E) None of the above41) Slack time in a network is theA) amount of time that an activity would
take assuming very unfavorable conditions.B) shortest amount of time that could be
required to complete the activity.C) amount of time that you would expect it
would take to complete the activity.D) difference between the expected
completion time of the project using pessimistic times and the expected completion
time of the project using optimistic times.E) amount of time that an activity can be
delayed without delaying the entire project.42) The first step in planning and
scheduling a project is to develop theA) employee scheduling plan.B) PERT/CPM network diagram.C) critical path.D) work breakdown structure.E) variance calculations for each
activity.43) Which of the following is not a
concept associated with CPM?A) normal timeB) probabilityC) normal costD) crash costE) deterministic network44) PERTA) assumes that we do not know ahead of
time what activities must be completed.B) assumes that activity time estimates
follow the normal probability distribution.C) is a network technique that uses three
time estimates for each activity in a project.D) is a deterministic network technique
that allows for project crashing.E) None of the above45) CPMA) assumes we do not know ahead of time
what activities must be completed.B) assumes that activity time estimates
follow the normal probability distribution.C) is a deterministic network technique
that allows for project crashing.D) is a network technique that allows
three time estimates for each activity in a project.E) None of the above46) Managers use the network analysis of
PERT and CPM to help themA) derive flexibility by identifying
noncritical activities.B) replan, reschedule, and reallocate
resources such as manpower and finances.C) plan, schedule, monitor, and control
large and complex projects.D) All of the aboveE) None of the above47) The expected time in PERT isA) a weighted average of the most
optimistic time, most pessimistic time, and four times the most likely time.B) the modal time of a beta distribution.C) a simple average of the most
optimistic, most likely, and most pessimistic times.D) the square root of the sum of the
variances of the activities on the critical path.E) None of the above48) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute
the PERT expected activity time for this activity.A) 8B) 6C) 7D) 9E) None of the above49) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 2, 5, and 14 days respectively,
compute the PERT expected activity time for this activity.A) 6B) 7C) 9D) 5E) None of the above50) Given an activity’s optimistic, most
likely, and pessimistic time estimates of 4, 14, and 18 days respectively,
compute the PERT expected activity time for this activity.A) 14B) 12C) 11D) 13E) None of the above