Activity A has a standard cost of $500 and them standard time to complete Activity A is 5 weeks

admin
July 2, 2020 0 Comment

1.

Activity A has a standard cost of $500 and the

standard time to complete Activity A is 5 weeks. The crash time for

Activity A is 3 weeks and the crash cost is $600. What is the crash cost

per week for Activity A?

                                        (Points : 3)

$50

$100

$150

$200

$300

                                     Question 2.

2.

Considering the following Activity-On-Node (AON) project (activity completion times are in days), how long will it take to complete the project?

.next.ecollege.com/CurrentCourse/GBA334_Quiz3_Ques_1.jpg”>

.next.ecollege.com/CurrentCourse/AON_General.docx”>Click here to view a Word version of the project.

                                        (Points : 3)

13 days

14 days

15 days

16 days

                                     Question 3.

3.

Considering the following Activity-On-Node (AON) project (activity completion times are in days), what is the slack time associated with activity D?

.next.ecollege.com/CurrentCourse/GBA334_Quiz3_Ques_1.jpg”>

.next.ecollege.com/CurrentCourse/AON_General.docx”>Click here to view a Word version of the project.

                                        (Points : 3)

0 days

1 day

2 days

3 days

                                     Question 4.

4.

Consider the following Activity-On-Node (AON)

PERT project. The three values that represent each activity’s completion

time (in days) correspond to an optimistic time, most likely time, and

pessimistic time, respectively. What is the standard deviation associated with the completion time of activity B?

.next.ecollege.com/CurrentCourse/GBA334_Quiz3_Ques_2.jpg”>

.next.ecollege.com/CurrentCourse/AON_PERT.docx”>Click here to view a Word version of the project.

                                        (Points : 3)

0.0245 days

0.6667 days

0.3145 days

0.3333 days

                                     Question 5.

5.

Consider the following Activity-On-Node (AON)

PERT project. The three values that represent each activity’s completion

time (in days) correspond to an optimistic time, most likely time, and

pessimistic time, respectively. What is the expected completion time of activity A?

.next.ecollege.com/CurrentCourse/GBA334_Quiz3_Ques_2.jpg”>

.next.ecollege.com/CurrentCourse/AON_PERT.docx”>Click here to view a Word version of the project.

                                        (Points : 3)

2 days

3 days

4 days

5 days

                                     Question 6.

6.

Jamie is planning a trip overseas. A variety

of activities must be completed before her departure. The following

table describes the relationships between these activities:

Immediate

Activity Predecessors

A –

B A

C A

D B, C

E B, C

F D, E

G F

Jamie was also able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 4

B 4

C 5

D 3

E 3

F 2

G 1

Considering the information above, what is the length of the project?

                                        (Points : 3)

11 days

12 days

14 days

15 days

                                     Question 7.

7.

Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate

Activity Predecessors

A –

B –

C A, B

D C

E C

F D, E

G E

H F, G

Also assume that the painters were able to estimate the activity times as shown in the table below:

Activity Time (Days)

A 3

B 2

C 4

D 5

E 3

F 2

G 4

H 2

Considering the information above, what is the earliest finish time for activity F?

                                        (Points : 3)

10 days

12 days

14 days

16 days

                                     Question 8.

8.

Consider the following set of activities that must be completed in order to prep a new home for painting:

Immediate

Activity Predecessors