101 Given the network shown in Figure 13-1n and the following information, what is the variance of the critical path?

admin
July 5, 2020 0 Comment

.101 Given the network shown in Figure 13-1
and the following information, what is the variance of the critical path?

Activity

Expected
time

Variance

A

3

2

B

5

3

C

6

3

D

4

1

E

4

1

F

4

2

G

6

2

H

7

2

(a) 16
(b) 7
(c) 9
(d) 8
(e) none of the above

}

PROBLEMS

13.102 Given:

Activity

Optimistic

Most Likely

Pessimistic

A

3

4

5

B

6

7

14

C

6

9

12

D

0.5

1

1.5

E

2

3

10

F

4

5

12

G

1

3

11

.gif”>

Determine:

(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.

}

13.103 A small software development project has five major activities. The times are estimated and provided in the
table below.

Activity

Immediate
Predecessor

a

m

b

A

2

5

8

B

10

10

10

C

A

4

7

10

D

B

2

5

14

E

C

3

3

3

(a) What is the expected completion time for this
project?
(b) What variance would be used in finding
probabilities of finishing by a certain time?

}

13.104 Development of a new deluxe version of a
particular software product is being considered. The activities necessary for the completion
of this are listed in the table below.

Activity

Normal Time

Crash Time

Normal Cost

Crash Cost

Immediate
Predecessor

A

4

3

2000

2600

B

2

1

2200

2800

C

3

3

500

500

D

8

4

2300

2600

A

E

6

3

900

1200

B

F

3

2

3000

4200

C

G

4

2

1400

2000

D,E

(a) What is the project completion date?
(b) What is the total cost required for completing this project on
normal time?
(c) If you wish to reduce the time required to complete this project
by one week, which activity should be crashed, and how much will this increase
the total cost?

}

13.105 Draw the PERT network
associated with the following activities.

Immediate Predecessor

A

B

A

C

A

D

B

E

B

F

C, E

G

A, D

H

F

I

F

J

G, H, I

}
13.106 Given:

Activity

Optimistic

Most
Likely

Pessimistic

A

3

4

5

B

6

7

14

C

2

3

10

D

6

9

12

E

4

5

12

F

1

3

11

G

1

2

9

H

2

5

8

I

1

4

7

.gif”>

Determine:

(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.

}

13.107 A small software development project has four major
activities. The times are estimated and
provided in the table below.

Activity

Immediate
Predecessor

a

m

b

A

2

5

8

B

A

3

6

9

C

A

4

7

10

D

B

2

5

14

E

D

3

3

3

F

C

6

8

10

G

E, F

1

1

1

H

C

6

10

14

I

G, H

3

4

5

(a) What is the expected completion time for this project?
(b) What variance would be used in finding probabilities of finishing
by a certain time?

}

13.108 Development of a new deluxe version of a
particular software product is being considered. The activities necessary for the completion
of this are listed in the table below.

Activity

Normal Time

Crash Time

Normal Cost

Crash Cost

Immediate
Predecessor

A

4

3

2,000

2,600

B

5

3

2,200

2,800

C

3

3

500

500

D

8

4

2,400

2,600

A

E

6

3

900

1,200

B

F

3

2

3,000

4,200

C

G

4

2

1,700

2,000

D,E

(a) If you wish to reduce the time required to complete this project
by two weeks, which activity(ies) should be crashed, and how much will this
increase the total cost?
(b)
What would be the added cost if you wanted to complete the project in
the minimum time possible?

}

SHORT ANSWER/ESSAY

13.109 PERT is the acronym for what?

}

13.110 In a PERT analysis,
how is the optimistic time defined?

}

13.111 CPM is the acronym
for what?

}

13.112 In PERT analysis, how
is the pessimistic activity time defined?

}

13.113 In PERT/CPM, what is meant by the critical
path?

.101 Given the network shown in Figure 13-1
and the following information, what is the variance of the critical path? ActivityExpected
timeVarianceA32B53C63D41E41F42G62H72 (a) 16 (b) 7 (c) 9 (d) 8 (e) none of the above }13.102 Given:ActivityOptimisticMost LikelyPessimisticA345B6714C6912D0.511.5E2310F4512G1311 Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. }13.103 A small software development project has five major activities. The times are estimated and provided in the
table below. ActivityImmediatePredecessorambA-258B-101010CA4710DB2514EC333 (a) What is the expected completion time for this
project? (b) What variance would be used in finding
probabilities of finishing by a certain time? }13.104 Development of a new deluxe version of a
particular software product is being considered. The activities necessary for the completion
of this are listed in the table below.ActivityNormal TimeCrash TimeNormal CostCrash CostImmediatePredecessorA4320002600-B2122002800-C33500500-D8423002600AE639001200BF3230004200CG4214002000D,E (a) What is the project completion date? (b) What is the total cost required for completing this project on
normal time? (c) If you wish to reduce the time required to complete this project
by one week, which activity should be crashed, and how much will this increase
the total cost?}13.105 Draw the PERT network
associated with the following activities. Immediate PredecessorA-BACADBEBFC, EGA, DHFIFJG, H, I}
13.106 Given:ActivityOptimisticMost
LikelyPessimisticA345B6714C2310D6912E4512F1311G129H258I147 Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. }13.107 A small software development project has four major
activities. The times are estimated and
provided in the table below. ActivityImmediatePredecessorambA-258BA369CA4710DB2514ED333FC6810GE, F111HC61014IG, H345 (a) What is the expected completion time for this project? (b) What variance would be used in finding probabilities of finishing
by a certain time? }13.108 Development of a new deluxe version of a
particular software product is being considered. The activities necessary for the completion
of this are listed in the table below.ActivityNormal TimeCrash TimeNormal CostCrash CostImmediatePredecessorA432,0002,600-B532,2002,800-C33500500-D842,4002,600AE639001,200BF323,0004,200CG421,7002,000D,E (a) If you wish to reduce the time required to complete this project
by two weeks, which activity(ies) should be crashed, and how much will this
increase the total cost? (b)
What would be the added cost if you wanted to complete the project in
the minimum time possible? }13.109 PERT is the acronym for what? }13.110 In a PERT analysis,
how is the optimistic time defined? }13.111 CPM is the acronym
for what? }13.112 In PERT analysis, how
is the pessimistic activity time defined? }13.113 In PERT/CPM, what is meant by the critical
path?